Founder & CEO
On October 9, 2026, the European Commission selected a second list of 46 strategic projects under Regulation (EU) 2024/1252 on critical raw materials. The projects are located in 16 member states and cover 15 of the 17 strategic raw materials listed in the regulation. They were chosen among 102 applications submitted across the Union.
The breakdown by value chain stage is as follows: 8 extraction projects, 11 processing projects, 19 recycling projects, and 8 integrated projects combining several activities. Strategic project status opens two doors: accelerated permitting procedures and easier access to financing.
This list follows the one from March 25, 2025, which covered 47 projects across 13 member states, and the 13 projects located outside the Union adopted in June 2025. The regulation entered into force on May 23, 2024. It sets European capacity benchmarks for 2030: 10 percent of annual consumption covered by extraction, 40 percent by processing, 25 percent by recycling.
The center of gravity shifts downstream
The first list was dominated by upstream activity: 25 extraction projects against 10 recycling projects. The second list reverses that order. Nineteen recycling projects, 11 processing projects, 8 extraction projects, plus 8 integrated projects. The path chosen now gives processing and recovery capacity on European soil as much weight as opening new mining sites.
For an industrial company, the practical point is not the number of projects. It is the nature of the flows they call for: production scrap, end-of-life batteries and magnets, metallurgical residues, secondary deposits. These flows often come from players that were not, until now, seen as raw material suppliers. They enter a scope where origin, composition, and treatment conditions must be documented.
Selection ripples down the chain
Applications are assessed by independent experts, based on technical feasibility and environmental, social and governance performance criteria. The project promoter answers for these criteria before the Commission. It cannot answer alone.
A project holding this status must meet shortened permitting deadlines and the conditions attached to its financing. Requests for evidence therefore move up the chain: origin of incoming flows, operating conditions, residue management, relations with host communities, subcontractor compliance. A supplier that cannot produce this evidence within the project timeline becomes a point of friction, then an option set aside in favor of another.
The same logic applies on the buying side. A buyer who wants to anchor a supply arrangement to a strategic project needs to know what is at stake: real capacity, permitting timeline, exposure to legal challenges, the promoter’s maturity on environmental and social issues. Selection measures potential. The ability to actually operate still has to be proven, project by project. This is the concrete expression of the dual regulatory and commercial pressure already described on this blog.
What an organization can do
First step: a position diagnostic. Which projects, which materials, and which member states is the organization actually exposed to, as a supplier, a buyer, or a financer. This work needs to be done business unit by business unit, because situations vary widely from one site to another, even within the same group.
Second step: assessment against a framework. On one side, the obligations under Regulation (EU) 2024/1252. On the other, the maturity of circular materials management for activities touching on recycling. A useful assessment produces a score by area, dated gaps, and a readout that top management can actually use. It feeds a prioritized action plan, then a roadmap tied to the ongoing transformation program, rather than opening a parallel workstream.
Third step: staying the course over time. The Commission has announced it will keep working on projects located outside the Union, the files already selected are moving forward, and documentation requirements are becoming clearer as financing takes shape. A monitoring setup that reviews the same scope at regular intervals, with the same questions and the same scoring method, makes it possible to track progress instead of rebuilding a status report every year. This is the use case Datamensio was designed for.